The project is using PRINCE2's recommended risk management procedure. In the 'identify' step, a risk was recorded in the risk register: ''If the 'accredited classroom-based course' is delayed, there is a threat that work on the 'e-learning course' will be delayed, resulting in the 'accredited e-learning course' not being ready for the 'pilot courses'.''
In the 'implement' step, a risk response was decided: ''Work will start incrementally on the 'e-learning course' whenever a part of the 'classroom-based training materials' gains accreditation''.

Is this appropriate, and why?

  • A

    Yes, because delivering incrementally will reduce the impact of the threat.

  • B

    Yes, because a risk response needs to be implemented for this major threat.

  • C

    No, because risks responses should be identified as part of the 'plan' step.

  • D

    No, because a risk action should be allocated to implement a response.