Q1 Single choice

What is the next action for improvement items identified during the Iteration Retrospective?

  • A

    They are entered as Stories in the Team Backlog

  • B

    They are ROAMed with the rest of the risks

  • C

    They are given to the Scrum Master/Team Coach who resolves them

  • D

    They are escalated to the Business Owners