Q4 Single choice

You work as the network administrator at ABC.com. Your responsibilities include maintaining the Project

Server 2010 environment. The company has multiple projects in progress at any one time. ABC.com employs

several Project Managers to manage the projects using the Project Server 2010 environment. Senior

management at ABC.com uses the Project Server 2010 environment to gain an overview of the progress of

the current projects. You receive a complaint from senior management that the progress of project tasks is

displayed in different formats. You have been asked to configure the Project Server 2010 environment so

that the progress of all project tasks is displayed as a percentage of work complete.

How should you configure the Project Server 2010 environment?

  • A

    You should create a custom view for the My Tasks page.

  • B

    You should update the Units field setting for all assignments.

  • C

    You should configure the Task Settings and Display options to enforce the specified progress reporting

    method.

  • D

    You should configure the timesheets settings to enable Single Entry Mode (SEM).