Exit 70-177 TS: Microsoft Project Server 2010, Configuring
Question 5 of 5
0% complete
Q5 Multiple choice

You work as a Project Manager at ABC.com. You are using the Project Server 2010 environment to manage a

complex project. ABC.com has six teams of users working on the project. Each team has a team leader.

ABC.com has released a policy that requires team leaders to have the ability to approve tasks in the

project. You, therefore, create a group named Team Leaders and add the users to the group. You now need to

configure the category permissions for the group.

Which three of the following category permissions should you assign to the Team Leaders group? (Choose three.)

Select all that apply.

  • A

    Edit Project Summary Fields.

  • B

    Accept Task Update Requests.

  • C

    Save Project to Project Server.

  • D

    Approve Timesheets.

  • E

    Assign Resources.

  • F

    Open Project.