Exit HPE2-W09 Aruba Data Center Network Specialist
Question 5 of 5
0% complete
Q5 Single choice

Refer to the exhibit.

which shows the topology tot an Ethernet Ring Protection Switching (ERPS) solution.

Is this a valid design for the control and protected VLANs on the VSX fabric 1 switches?

Solution: Ring 1, instance 1:

control VLAN: 1000 protected VLANs: 51-135 Ring 1, Instance 2:

control VLAN: 1000 protected VLANs: 136-220 Ring 2, Instance 1: control VLAN:
1001 protected VLANs: 181 -200 Ring 2, Instance 2: control VLAN: 1001 protected VLANs: 201 -220

  • A

    Yes

  • B

    No