Which of the following represents the EAC of an ongoing project with an AC of $100,000, a CV of $10,000 and an ETC of $50,000?

  • A

    $90,000

  • B

    $140,000

  • C

    $150,000

  • D

    $160,000

  • E

    The project is taking longer than the estimated schedule.

  • F

    The project is costing less than the estimated budget.

  • G

    The project is taking less time than the estimated schedule.

  • H

    The project is costing more than the estimated budget.