Q5 Single choice

A project manager is managing a project that is scheduled to take ten months to complete. The project is in its sixth month and $450,000 has been spent. The project budget is $990,000.

Which of the following will the project manager use to determine the budgeted cost of work scheduled?

  • A

    Estimate to completion

  • B

    Planned value

  • C

    Cost performance index

  • D

    Budget at completion