Exit MB5-858 Managing Microsoft Dynamics Implementations
Question 1 of 5
0% complete
Q1 Multiple choice

You explain to your customer that you will use a formal project status report. How should you describe this document to your customer? Choose the 2 that apply.

Select all that apply.

  • A

    The status report is a document prepared by the customer project manager on a weekly basis.
    It describes overall health status of the project, including decisions made and vacation schedules.

  • B

    The status report is a document prepared by the consulting project manager on a weekly basis.
    It describes overall health status of the project, including decisions made and vacation schedules.

  • C

    The status report is a document that is first reviewed with the project team through an internal weekly team status meeting and then presented to the customer.

  • D

    The status report is a document that is first reviewed with the key user team through an internal weekly team status meeting and then presented to the consulting project manager.