Exit PMI-RMP PMI Risk Management Professional (PMI-RMP)
Question 1 of 5
0% complete
Q1 Single choice

You are the project manager of QSL project for your organization. You are working with your project team and several key stakeholders to create a diagram that shows how various elements of a system interrelate and the mechanism of causation within the system.

What diagramming technique are you using as a part of the risk identification process?

  • A

    Predecessor and successor diagramming

  • B

    System or process flowcharts

  • C

    Cause and effect diagrams

  • D

    Influence diagrams

Previous Next