Exit PMI-RMP PMI Risk Management Professional (PMI-RMP)
Question 2 of 5
0% complete
Q2 Single choice

A supplier Is delayed in delivering fuel for a project. The project manager anticipated this risk and is requesting fuel from another supplier. When speaking with the other supplier, a new risk appears because fulfilling the order will cause delays with several other projects.

After performing a detailed analysis, what should the risk manager do?

  • A

    Escalate the problem to the project sponsors.

  • B

    Execute the approved risk response plan.

  • C

    Negotiate with the supplier to resolve the problem.

  • D

    Assign a team member to update the issue leg.