PESTLE, TECOP, and SPECTRUM are three examples of prompt lists that can be used during risk management activities.
Prompt lists are used to do which of the following?

  • A

    Simulate risk identification.

  • B

    Perform a simulation with all prompted risks varying simultaneously.

  • C

    Identity basic causes of risks of more fundamental forces.

  • D

    Achieve the relative weighting of the risks.