You use Project Professional 2010 to manage a project. John, a team member, is over-allocated.

You need to identify the dates on which the over-allocation occurs.

What should you do?

  • A

    Use the default Leveling Gantt view.

  • B

    Use the Team Planner view.

  • C

    Use the Timeline view.

  • D

    Use the Task Information dialog box.

  • E

    Use the Task Details Form.