Exit 70-178 Microsoft Project 2010, Managing Projects
Question 4 of 5
0% complete
Q4 Single choice

You need to ensure that you can view only the tasks on your projects critical path.

What should you do?

  • A

    On the Advanced tab of the Project 2010 options, select the Calculate multiple critical paths check box.

  • B

    View the projects Gantt chart and apply the Critical group.

  • C

    View the project's Gantt chart and apply the Critical filter.

  • D

    On the Advanced tab of the Project 2010 options, modify the Tasks are critical if slack is less than or equal to option.