Exit 70-178 Microsoft Project 2010, Managing Projects
Question 2 of 5
0% complete
Q2 Single choice

You have a project schedule in progress.

You need to view only the tasks that currently affect the overall completion date.

What should you do in the Gantt Chart view?

  • A

    Apply the Priority group.

  • B

    Apply the Incomplete Tasks filter.

  • C

    Apply the Late Tasks filter.

  • D

    Apply the Critical Tasks filter.

  • E

    Apply the Status group.