Exit 70-178 Microsoft Project 2010, Managing Projects
Question 5 of 5
0% complete
Q5 Single choice

You track all costs on your project. You need to track task-level airfare costs that do not depend on the amount of work or duration of a task.

What should you do?

  • A

    Use a work type resource.

  • B

    Create a custom field and capture travel costs at the project level.

  • C

    Use a budget resource.

  • D

    Use a cost type resource.