Exit 70-178 Microsoft Project 2010, Managing Projects
Question 3 of 5
0% complete
Q3 Single choice

2. Task 1 is the predecessor for Task
2. You need to ensure that when the duration of Task 1 changes, the scheduled start date for Task 2 does not change automatically.

How should you configure Task 2?

  • A

    Set the task type to Fixed Duration.

  • B

    Set the lag to two elapsed days (2ed).

  • C

    Set the constraint type to Start No Earlier Than.

  • D

    Set the schedule mode to Manually Scheduled.